Sweid Family Home

Construction Schedule

There are no builds

Construction Checklist

Note: The list below is grouped into expected completion date.

Date has not been set

Install Porch Rail & Lattice

Friday, February 02, 2007

Install Interior Trim
Paint Interior Doors
Paint Interior Trim
Paint Interior Walls
Prime Interior Walls

Friday, February 09, 2007

Install Closet Shelving
Install Interior Doors & Knobs
Install Kitchen & Bath Cabinets
Install Porch Rail & Lattice

Friday, February 16, 2007

Clean Up
Install Appliances
Touch Up Painting

Friday, February 23, 2007

Landscaping

Saturday, October 20, 2007

Build Floor Beam
Install Floor Decking
Install Floor System
Install Termite Shield, Sill Sealer, Sill Plate
Insulate Crawlspace
Spread Pea Gravel

Saturday, October 27, 2007

Frame Exterior Walls
Frame Interior Walls
Line & Brace Exterior Walls

Saturday, November 03, 2007

Foam Exterior Walls
Frame Porch
Line & Brace Interior Walls
Sheath Exterior Walls

Saturday, November 10, 2007

Install Crawlspace Vapor Barrier
Install Drip Edge
Install Roof Felt
Install Roof Sheathing
Install Siding
Install Siding Starter Strips
Install Soffitt
Install Truss Clips
Set Roof Trusses
Trim Doors
Trim Windows

Saturday, November 17, 2007

Install Blocking for Cabinets, Grab-bars
Install Drywall Backing

Saturday, November 24, 2007

Install Doors
Install Roof Shingles
Install Windows

Saturday, January 26, 2008

Install Electrical
Install HVAC
Install Plumbing

Family Biography

Written By Champaign County Habitat Affiliate

Project Blog

No blog posts

Project Photos

Special Thanks

To the Providers of Our Free Lunches: Chipolte, Silver Mine Subs, Papa John's Pizza, Treva Ellison Volunteer Construction Leaders: Jesse Mesengale, Helen Miller, Jack Collins